PolySteel Piping Systems - Australian made by Duraduct

Home PageEmail PolySteelSubscribe to the PolySteel Newsletter


PolySteel Handling Installation and
Maintenance Instructions
  



The handling, installation and maintenance of PolySteel pipe work should only be carried out by trained personnel. The following information is provided as a supplement to standard handling and installation procedures and
good safe work practices.

Pipe Handling

Lifting, moving and positioning PolySteel spools must be conducted by locating slings or spreader bars at two
or more points along the length of the pipe in order to support the load in a safe and secure manner.
It will also minimise the stress induced due to pipe bending during lifting.
Under no circumstances must the pipe spools be lifted from the centre or one end only.




Pipe Supports

Spacing for pipe supports can vary for each individual project and assistance from Duriduct technical support personnel should be sought if there is any doubt as to spacing and load requirements.

It is important that pipe supports be designed so that pipe flanges have sufficient clearance from the
ground and surrounding structures.

The following procedures should be taken into consideration where PolySteel piping is to be placed directly
on the ground without supports:

-- Uneven or unstable soil should be compacted so as to provide adequate support along the entire pipe run.

-- Rock should be removed from the pipe bed to ensure that the pipe load does not rest on the rock.

-- Soil adjacent the flange joints must be “scalloped” away to prevent the flanges from sitting the soil

Pipe Preparation and Installation

Flange protection

PolySteel piping spools and fittings are shipped with backing boards or flange protection fitted.
In order to prevent damage to the flange sealing face the protective covers should not be removed until
the flanges are ready to be bolted into position.
If covers are removed for inspection purposes prior to installation they should be replaced.
If pipe is removed from the pipeline for any reason protective flange covers should be fitted.

Rubber joint gaskets
Rubber ring joint gaskets may be specified in higher pipeline operating pressure applications (over 10 bar - 1000kPa) or piping systems of such length that thermal stresses may result in deformation of the plastic sealing face.
In these applications a reliable seal can be achieved using a 1.6mm ring joint such as a Klinger PSM-AS
For further advice about PolySteel jointing requirements contact Duriduct technical support.

Pipe Installation Preparation
-- Prepare the laying site in accordance with appropriate and safe working practice
-- Provide uniform pipe support at all times
-- Align the mating flanges to ensure they can be brought together squarely
-- Support pipe by crane during bolt tightening

Pipe Jointing Procedure
-- PolySteel piping spools leave the factory with one flanged end fitted with a backing board and the “poly” liner flange face fitted tightly against the steel flange. The other flanged end of the spool will have the “poly” liner
and its flange face protruding from the steel flange. (Refer Fig 1 below). This protrusion is a design feature
and the extent of protrusion will vary according to the length of the spool and ambient temperature.



-- During installation the liner will be compressed inside the steel pipe casing by sequentially tightening flange bolts
in stages until the “poly” flange meets the steel flange. (Refer Fig 2 below). Jointing is achieved by fitting two or three extended length compression bolts or threaded rod to the connecting flanges and tightening evenly until
the distance between jointing flanges allows specified bolts to be fitted. Compression bolts should be tightened alternatively from adjacent sides of the flange and no more than one turn of the nut at a time.



-- Spacer rings (Refer Fig 3 below), if specified, should be fitted before inserting the extended length compression bolts. The spacer ring can be designed to fit inside or outside the bolt circle, depending on the size and standard
of the flange specified.



-- Once the correct flange bolt length is reached during the compression process the specified flange bolts,
nuts and washers are installed and the extended compression bolts or threaded rod removed and replaced with
the specified bolts. Flange bolts should be tightened in a sequence (Refer Fig 4 and 5 below).





Leaking joint during Installation
In the event of a leaking joint during testing of the pipeline and providing the bolts where the leak has occurred
have been properly tightened then they should not be further tightened otherwise permanent damage to the
sealing face could result.

The following process of rectification is recommended:

-- The bolts on the opposite side to the leak should be loosened a half turn at a time and those on the
leaking side tightened by the same amount.

-- If the leak persists the bolts should be removed and the sealing face examined for damage such as scratches
and dents across the face which could provide a leak path.

-- Any damage which does not exceed 10% of the liner thickness at the sealing face may be repaired by hand polishing using a very fine abrasive cloth or paper, taking care to maintain an even liner thickness across
the whole sealing face.

Avoid heat damage
Avoid welding, brazing, soldering or flame cutting to or adjacent to PolySteel pipe and fittings, because
excessive heat can permanently damage the “poly” liner.


 


 

Home PageEmail PolySteelSubscribe to our Newsletter

About PolySteel   Contact Us    |    Who are we   |    What we do    |    How we do Business    |    Join our Newsletter
Products & Services
   PolySteel Pipe    |    PolySteel Fittings    |    PolySteel Pipe Jointing    |    PolySteel Vacuum Breaks
More Products & Services    Engineering Services    |    Pipeline Installation Services    |    PolySteel Office Locations
Product Information    Advantages of PolySteel    |    Manufacturing Process    |    Pipeline Material Selection
More Product Information    PolySteel Pressure Capacities    |    Product Specifications    |    PolySteel Handling & Maintenance
Markets & Installations
   Quality Assurance     |     Typical Markets     |     Typical Customers     |     Website Terms & Conditions
Our Other Companies ►   Duraduct    |    Stainless Tanks    |    Stainless Tube Mills    |    STM Fences

PolySteel - Address: 193 Beechboro Road South, Embleton, Western Australia, Australia 6062
Click here to email PolySteel directly